From: Assistance to Project Manager Subject: Work Breakdown Structure & Time-Phased Budget
The work breakdown structure for the Care+ Case Management System in the Managed Care Department is illustrated in the Gantt-Chart, which may be found in the Appendix to this memorandum. A total of 10 tasks were identified for the project. The tasks, together with the assumptions underlying the tasks and their relationships, are as follows:
Order hardware & backup software: The assumptions are that (a) project concept planning is complete and (b) servers (hardware) and backup softw